Land Clearing Projects in Elgin, Texas

Every job on this page happened in Elgin or the country right around it, in Bastrop County. The acreage, the machine, the days on site and what it cost are the real numbers off the job.

Elgin sits in post oak savanna, so the work here is usually understory: yaupon and volunteer brush closing in under oaks the owner wants to keep. That is why most of these are selective jobs rather than full clearing.

6documented jobs in Elgin
280acres cleared
84days on the ground

10 Acre Full Clearing for a Commercial Site in Elgin, Texas

August 2026

Acreage10 Acre
ServiceFull Clearing for a Commercial Site
EquipmentWeiler M860A Forestry Mulcher
Days on site4
Cost$16,000 to $17,000
Standing brush and volunteer trees on the Elgin tract at dusk, with the mulcher working the edge
Standing brush and volunteer trees on the Elgin tract at dusk, with the mulcher working the edge
Late evening light through the remaining treeline as the mulcher works the standing growth
Late evening light through the remaining treeline as the mulcher works the standing growth
The same tract opened up to bare ground, clear to the treeline
The same tract opened up to bare ground, clear to the treeline
Ten acres finished, with the overhead powerline corridor running across the cleared ground
Ten acres finished, with the overhead powerline corridor running across the cleared ground

Ten acres in Elgin taken down to open ground for a commercial build. This was a clear cut rather than selective work, so the brush, the volunteer trees and the understory all came out and the tract was left open and workable for the trades that follow.

Four days on site with the Weiler M860A. The photographs below are the two ends of the job. The first pair is standing growth in the evening light on the way in, the second pair is the same tract opened up with the powerline corridor running across it.

Elgin sits in the Post Oak Savannah, where sandy loam runs over clay and post oak, yaupon and greenbrier come back hard on any ground left alone. On a commercial site that matters after the machine leaves, because whatever is left in the ground is what comes back first.

What made it tricky

The corridor crossing this tract is a live LCRA right of way, and the job requirement was simple and absolute: no contact with the energized lines. That set where the machine could sit and how high the head could come up, so the ground along the corridor was taken slower and more deliberately than the open acreage.

6 Acre Selective Forestry Mulching in Elgin, Texas

August 2026

Acreage6 Acre
ServiceSelective Forestry Mulching
EquipmentWeiler M860A Forestry Mulcher
Days on site2
Cost$9,000 to $10,000
Open oak woodland in Elgin Texas after selective forestry mulching removed the understory brush
Open oak woodland in Elgin Texas after selective forestry mulching removed the understory brush
View from the cab of the mulcher facing standing yaupon and brush before clearing in Elgin Texas
View from the cab of the mulcher facing standing yaupon and brush before clearing in Elgin Texas
View from the cab over ground cleared of understory brush with mature oaks left standing in Elgin Texas
View from the cab over ground cleared of understory brush with mature oaks left standing in Elgin Texas

This one was a pasture buy back. Six acres east of Elgin had closed in with yaupon and volunteer brush under a canopy of post oaks, and the owner wanted the grass back without losing the shade. The rule on the ground was simple: anything under six inches in diameter goes, anything bigger stays.

The Weiler M860A worked the understory at ground level for two days. Nothing was hauled off and nothing was burned. What was standing brush on the first morning was a mulch layer by the second afternoon, and that layer holds moisture and feeds the soil while the grass comes back.

Two of the photos below are the same vantage point from the cab, before and after.

What made it tricky

Selective work only. Every tree over six inches in diameter had to stay, so the machine worked around the oaks instead of through them.

Read the full write up on this project

4 Acre Selective Clearing and Yaupon Removal in Elgin, Texas

Acreage4 Acre
ServiceSelective Clearing and Yaupon Removal
EquipmentWeiler M860A Forestry Mulcher
Days on site1
Cost$4,000 to $5,000

Four acres of yaupon and brush taken out from under the cedar elms and oaks in one day. Choked understory to park like woods, with every canopy tree left standing.

Read the full write up on this project

8 Acre Full Brush Clearing and Invasive Tree Removal in Elgin, Texas

Acreage8 Acre
ServiceFull Brush Clearing and Invasive Tree Removal
EquipmentTigercat M726G Forestry Mulcher
Days on site3
Cost$10,000 to $12,000

Eight acres of pasture taken back from invasive brush and volunteer trees with the high horsepower mulcher. Three days on site, nothing hauled off.

Read the full write up on this project

125 Acre Pasture Reclamation in Elgin, Texas

Acreage125 Acre
ServicePasture Reclamation
EquipmentTigercat M726G Forestry Mulcher
Days on site37
Cost$120,000 to $130,000

One hundred and twenty five acres of overgrown pasture put back into grass. Thirty seven days on the ground with the high horsepower mulcher, working the property in blocks so the owner kept access throughout.

Read the full write up on this project

127 Acre Full Land Clearing for an LCRA Project in Elgin, Texas

Acreage127 Acre
ServiceFull Land Clearing for an LCRA Project
EquipmentTigercat M726G Forestry Mulcher
Days on site37
Cost$125,000 to $130,000

One hundred and twenty seven acres cleared to spec for an LCRA project, the largest single job we have run in Elgin.

Read the full write up on this project